Every precast unit supplied for Perth’s Armadale line elevated rail reduced embodied carbon without compromising strength, with recycled water used to clean the concrete beams.
Humes, a subsidiary of Concrete Institute Gold member Holcim, revealed that concrete from a dedicated precast facility it built for the Armadale Line Upgrade Alliance’s Metronet Victoria Park-Canning Level Crossing Removal Project in Perth now supports almost 4km of elevated rail line.
The facility in Midland produced 57,000 tonnes of precast concrete. Up to 10 precast beams were transported and lifted into place each night by cranes.
“Each L-beam, used to construct the rail corridor walls, is a prestressed concrete beam around 30 m-long that weighs 130 tonnes,” Humes stated. “Steel strands tensioned in the prestress bed allow the beam to carry rail loads between supports.”
Manufacturing offsite allowed production to run ahead of construction, according to the company. Casting at ground level in controlled factory conditions also moved much of the work at height away from the rail corridor and ensured consistent quality control.
Throughout production, bottlenecks had to be identified and timing each manufacturing step, adjusting the process as necessary, was essential. Humes revealed that sensors cast into each beam tracked the concrete’s temperature as it cured.
Humes supplied the precast concrete to the Armadale Line Upgrade Alliance which comprised Acciona, BMD, and Concrete Institute Silver members, WSP and AECOM. The project was completed in October 2025.
Image: Cranes lift a precast beam into place on the elevated Armadale Line during night works. Up to 10 beams travelled from the Midland facility to the site each night. Credit: Holcim.